The photovoltaic installation will consist of two solar plants of 50 MWp each, totaling a capacity of 100 MWp. It will be located in the province of Granada and will be built on an area of approximately 193 Ha.
The installation will consist of the most advanced solar technology, with 238,000 polycrystalline silicon photovoltaic modules that will occupy a net catchment area of 526,000 sqm. The modules will be mounted on structures with one axis tracking system and the produced direct current will be transformed to alternating current by string inverters with 174 kVA nominal power.
Expected specific production is 2,105 kWh/kWp, to obtain an average annual production of 211 GWh, equivalent to an average annual consumption in Spain of 65,123 households.
Energy evacuation will be carried out through 30/220 kV elevator transformers located in a high voltage substation common to both plants. The common substation will have a collector/elevator configuration. From this substation, it will connect to the collector substation Granada 1 through a 220 kV high voltage line, and next, it will connect to the expected renewable position in a REE’s planned 220 kV substation through a 220 kV common line.